New house assistance for Kadek Yudiantika in Br. Dinas Lambo, Pedawa, Buleleng

On 20 January 2025, we finished building a new house for Kadek Yudiantika; an underprivileged family in Banjar Dinas Lambo, Pedawa Village, Banjar District, Buleleng Regency.

The specifications for the house assistance program are as follows:

  • 2 bedrooms each measuring 3 m x 3 m
  • Terrace measuring 2 m x 6 m
  • Total building area 5 m x 6 m = 30 m2
  • Ceramic floor
  • Inside wall: plastered and painted bricks
  • Front side/terrace wall: plastered and painted bricks
  • Outside and back wall: unplastered brick
  • Roof: spandex

Donor for this house assistance program is: Ekajaya Fast Ferry (PT. Bali Eka Jaya).

The following is the process of implementing the housing assistance program:

  • November 29, 2024; BCC team and donor conducted a survey at Kadek Yudiantika house.
  • 11 – 13 December 2024;
    1) Coordinate with Kadek Yudiantika and family, to determine the location of the building, and find a good day to start building the house.
    2) Coordinate with local volunteer; Gede Wiradana (0823-2261-4376) to help supervise the project so that the construction of the house is in accordance with the specifications and costs that have been determined.
    3) Coordinate with the appointed builder to explain the specifications of the house and the cost of building the house.
  • December 19, 2024; start building the house
  • January 20, 2025; the house has been completed.

The following is documentation during the construction of the house.

 