The house reconstruction specifications are as follows:

  • House wide: 4 m x 5 m
    – Bed room: 3 m x 3 m
    – Bath room: 2 m x 1 m
    – Kitchen: 2 m x 2 m
  • The total wide of the house: 20 m2
  • Floor: cement finished
  • Wall: Concrete Brick roughly coated
  • Wall Height: 3 m
  • Squat toilet
  • Small bath tub
  • Roof: asbestos
  • Contractor: Mr. Sumardi (08135318544)
  • Cost: IDR 1,000,000 / m2
  • Total Cost: IDR 20,000,000

On 31st of March of 2015, the payment for the construction of 2 houses had been done to Mr. Sumardi; the contractor, below are the detail of the payment;

  • Ni Wayan Sare; house wide 20 m2 x IDR 1 Million/m2 = IDR 20 Million
  • Ni Nyoman Alit; house wide 12 m2 x IDR 1 Million/m2 = IDR 12 Million

Total payment is IDR 32 million. Payment receipt attached Bill; BCC Cheque dan receipt.

The contributors name lists for this house reconstruction donation are;

  1. Rudy Laurens family
  2. Hendry Widjojo family
  3. Fedy Romamti family
  4. Eka Nusantoro
  5. JA
  6. Eny Rahayu
  7. Susanto Akiong
  8. Kevin Chandra
  9. NK

Below are the time lines and processes of the house reconstruction donation:

  • February 27th 2015; collecting the information which is related to the planning of house reconstruction donation, and also coordinating with the family involved and local contractor.
  • March 28th 2015; showing the project location to appointed contractor; Mr. Sumardi (081353185444). Coordinating with the involved family and the hire to discuss about the position of the building and finding the date to start the construction.
  • April 1st 2015; The house reconstruction projects was started.
  • April 18 2015; Monitor the progress of the project and arrange a meeting with the chief of Culik Village; Mr. Ketut Sukarta to build a coordination in relation to the project.
  • April 23rd 2015; the construction had been finished and handed over to Ni Wayan Sare

Below we provide some of the documentation.

1-bedah-rumah-wayan-sare
2-bedah-rumah-wayan-sare
3-bedah-rumah-wayan-sare
4-bedah-rumah-wayan-sare
5-bedah-rumah-wayan-sare
6-bedah-rumah-wayan-sare
7-bedah-rumah-wayan-sare
8-bedah-rumah-wayan-sare
9-bedah-rumah-wayan-sare
10-bedah-rumah-wayan-sare
11-bedah-rumah-wayan-sare
12-bedah-rumah-wayan-sare

Write a Comment


Social Media

WhatsApp 087861943126
WhatsApp 081239993144
LINE 087861943126
LINE 081239993144
Telegram 081239993144