On June 7th, 2019 we finished building a simple house for the family of Gusti Wayan Sarjana; an underprivileged family who live in an ex-pig pen in Dusun Dajan Peken, Timpag Village, Kerambitan District, Tabanan Regency.


The specifications of the house renovation program are as follows:
- 2 bedrooms, each with a size of 2.5 m x 2.5 m
- Terrace with a size of 1 m x 5 m
- Total building area is 17.50 m2
- Ceramic floor
- Inner wall / bedroom: brick, plastered and painted
- Outer wall, the front side / terrace: brick, plastered and painted
- Outer side and back wall: the brick is not plastered
- Ceiling: kalsiboard
- Roof: tile
Total construction cost: Rp. 20,500,000, –


The list of donors for this house renovation program is as follows:
- Sang Ayu Githashanti
- Meida Pratiwi
- Lestari
- Yuni Pande
- Ayu Indrayani
- Bagus Wima
- Hari Wisnu
- Kanaya Duarsa
- Yasodhara Duarsa
- Yasodha Duarsa
- Klg Fong Tandam
- Janz Sudiantika
- Laila
- Luh Ayu Purnayatri
- Ngurah Suardana
- AAI Mirah Wirawati
- Mahawira
- Angelmartz
- Dhananjaya Wibowo
- Wayan Desi
- Ida Bagus Ascharya
- Made Tirta
- Komang Wiprama
- Alit Putra Christ M.S.
- Gunawan
- Oka Suyatna
- Daniesh Musthafa
- Semarindo Law Firm
- Laksmi
- Radha Kurniawan
- Kadek Suwaryati
- I Putu Krisna Parama Arta
- Sudiastiti
- Kadek Sugiarta
- IGN Agung Suryanegara
- Made Gandhi Arsawiguna
- Magdalena Sri Lestari
- Ni Nyoman Madiani
- Hamdani
The following is the implementation process of the house renovation assistance program:
- April 4th, 2019; the BCC team conducted a survey of the house.
- 5-9 May 2019;
– Coordinated with beneficiary and his family and the local dusun head to determine the location of the building, and look for a good day to begin the process of building the house.
– Coordinated with the BCC Volunteers in Tabanan; Ni Made Ayu Suastuti (0822-4746-3663) to help supervise the project so that the construction of house is in accordance with the specifications and costs that have been determined.
– Coordinated with the appointed builder to explain the specifications of the house and the cost of building the house. - May 10th, 2019; started the process of building a house.
- June 7th, 2019; the house renovation was completed and handed over to the beneficiary.
Here are some documentation during the house renovation.
Address: Dusun Dajan Peken, Timpag Village, Kerambitan District, Tabanan Regency.
Coordinates: 8°29’06.9″S 115°05’49.4″E (View on Google Maps)